Project Details
Lanco Power International Pte. Ltd. will develop a gas based combined cycle dual fuel power plant on 23.6 acres land within the Sirajganj power hub at Saidabad union of Sirajang Sadar upazila under Sirajganj district. This project consists of one (1) dual fuel combustion turbine (CT), One (1) Heat Recovery Steam Generator and one (1) Steam Turbine Generator, 36,000 m3 HSD storage facility, a 60 m stack, 1.5 km gas pipeline, 3 km HSD intake pipeline from Bangbabandhu Bridge West Railway Station and 4 km long water intake pipeline from Jamuna River to power plant. The project will require approximately 361.75 m3/hr water during operation phase.
Sirajganj
Lanco Power International Pte. Limited
Whether you have a project in mind and you’re looking for a reliable construction partner or you’re looking to take the next step in your career, we want to hear from you!