Project Details
LHBL is operating an integrated dry process Cement
Manufacturing Plant with a cement production capacity of 1.7 million tons per
annum (million TPA) at Noarai, Chhatak, Sunamganj.
The daily requirement of coal will be around 700 tons for
operating the plant which may vary slightly based on the calorific value of the
coal/pet coke. LHBL will procure the coal/pet coke from the authorized coal
importers in Bangladesh and will receive it through its existing jetty. To use
the coal in the burning process it needs to be grinded for getting the heat
recovery from the coal. LHBL will install a coal mill to ensure coal grinding
at the rate of 40 tons per hour to use in the clinkerization process. The coal
mill will be installed inside the existing plant.
After receiving the coal from the authorized vendors, the
coal will be stored in covered storage inside the plant premises. The covered
coal storage capacity will be approximately 16,000 tons. From the covered
storage, the coal will be transported by belt conveyor to its coal mill. Here
the coal will be grinded and will be stored in a Silo. From the silo, fine coal
will be fed to the calciner burner and the Kiln burner for the clinkerization
process.
The process and the coal mill will be designed to grind coal
as well as to adopt any future requirements if required.
LafargeHolcim Bangladesh Limited
Chhatak, Sunamganj, Bangladesh
Whether you have a project in mind and you’re looking for a reliable construction partner or you’re looking to take the next step in your career, we want to hear from you!